Design and manage procurement route
Contents |
[edit] Introduction
The design and manage procurement route shares several characteristics of management contracting.
Under this arrangement, the works are constructed by a number of different works contractors who report to a management contractor who is selected early in the process. The management contractor assumes responsibility for the other contractors and the design team. This procurement approach is suitable for large, complex projects or fast track projects.
It may also be a preferred method when the client wishes to have one point of contact who is responsible for everything. A single point of contact is also the case with the design and build procurement route, although some clients feel this route is only appropriate for simple projects where design quality is not the first priority.
[edit] Variations
There are two common variations of the design and manage procurement route:
- The organisation is paid to design and manage the work and delivers the project by hiring subcontractors to design and construct the project.
- The organisation is paid as a consultant to act as the agent of the client to design and manage the work by obtaining subcontract tenders from works contractors who then each enter into a direct contract with the client.
[edit] Advantages and disadvantages
Potential benefits to the design and manage procurement route include:
- A collaborative relationship between the design and manage contractor and the client.
- Fewer delays caused by a lack of information or miscommunication.
- Clearer delineation of overall financial responsibilities for the default of sub-contractors.
Possible negative aspects of the design and manage procurement process include:
- The duplication of resources between trade contractors and the design and manage contractor, resulting in a higher prices.
- A lack of an established contract sum, resulting in an estimate created by the quantity surveyor and then endorsed by the design and manage contractor; it is then confirmed along the way as tendering progresses and the works proceed.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding..